Solutions & EPC

One contract between you and a working plant.

Storage projects fail in the gaps: between the battery supplier and the EPC contractor, the PCS vendor and the protection engineer, the commissioning team and the O&M crew. We close those gaps by owning them.

Segment range0.5 MWh → 500 MWh
Contract formsSupply · EPC · EPC + O&M
DeliveryPan-India, from Ahmedabad

Segments

Three ways storage gets bought in India.

Sizing logic differs by segment far more than the hardware does. We start from the data that decides the outcome — a PPA profile, a 15-minute load curve, or a generation profile with an export limit.

Utility & IPP

Grid-scale plants

50 MWh to 500 MWh, tendered or bilateral. Sized against the PPA profile, ramp obligations and the grid code at the interconnection point.

  • Block 5.0 × n, PCS, transformer, protection
  • EMS/SCADA with revenue-grade metering
  • Grid compliance and metering coordination

Typical: 20 blocks = 100 MWh at 50 MW / 2 h

C&I

Behind the meter

0.5 MWh to 20 MWh at a factory, campus or cold store. Sized from interval data against demand charges, DG running hours and outage cost.

  • Rack 418 or Block 5.0, LT/HT integration
  • Peak shaving, DG displacement, backup
  • Monitoring with a monthly performance report

Payback modelled before proposal, not after

Solar + storage

Co-located with PV

DC-coupled or AC-coupled at an existing or new solar plant, to shift generation into the evening peak or hold inside an export limit.

  • DC/DC or AC coupling, per connection study
  • EMS coordinating PV, storage and export
  • Curtailment recovery and firming

Designed with the inverter, not around it

We are in ramp-up, and we bid accordingly. If your commissioning date falls outside our qualification window, we will say so at the first meeting rather than after the LOI. Where we cannot deliver on time, we will tell you who can.

Scope

Who does what, in writing.

A turnkey EPC claim means nothing without a scope matrix. This is ours, before contract. The final allocation is agreed per project and recorded in the contract schedule.

Responsibility matrix by project activity
Activity GESS Shared Client
Load, tariff or generation study✓
System sizing and block count✓
Electrical single-line and protection study✓
Civil, foundation and layout design✓
Fire strategy and statutory approvals✓
Cell, module, rack and block supply✓
PCS, transformer and switchgear✓
Balance of plant and cabling✓
Transport and site logistics✓
Installation and mechanical completion✓
Testing, commissioning and grid compliance✓
Interconnection, metering and utility liaison✓
O&M, monitoring and performance reporting✓

Supply-only engagements contract the manufacturing and FAT rows only, with commissioning advisory.

Process

From enquiry to commercial operation.

Indicative durations for a 50 MWh plant. C&I projects compress the middle stages considerably; utility projects extend them.

  1. 01 Enquiry and dataLoad profile, single-line, site plan, tariff or PPA, target COD Day 0
  2. 02 Sizing and proposalBlock count, layout, PCS selection, indicative price and payback 5–10 days
  3. 03 Engineering and approvalsGA drawings, protection settings, fire strategy, interface schedule 4–8 weeks
  4. 04 Manufacturing and FATModule, rack and block build; witnessed factory acceptance test 10–16 weeks
  5. 05 Logistics and installationProtected transport, set-down, DC and MV connection, BoP 4–8 weeks
  6. 06 Commissioning and CODCapacity test, RTE, protection tests, grid compliance, handover 2–4 weeks
  7. 07 OperationsMonitoring, scheduled service, spares, performance reporting Contract term

Commercial

Three contract forms.

The same hardware, three risk allocations. Which one is right depends on how much engineering you keep in-house.

A

Supply only

Modules, racks or blocks delivered ex-works or DAP, with FAT records and commissioning advisory. Your EPC contractor installs.

  • Equipment and warranty
  • FAT documentation
  • Advisory during commissioning

B

Turnkey EPC

Design, supply, install, test and commission to a single completion date and a single performance guarantee.

  • Single point of accountability
  • Capacity and RTE guarantee at COD
  • Liquidated damages per contract

C

EPC + O&M

Turnkey delivery plus a multi-year service contract: monitoring, scheduled maintenance, spares and availability commitment.

  • Availability and response SLA
  • Annual capacity-retention test
  • Remote monitoring and reporting

Health, safety & environment

Batteries are an industrial hazard. We treat them that way.

Site safety is not a page in a brochure. Installation crews work to a method statement and risk assessment per site, with DC isolation procedures written for this equipment and a permit-to-work regime that covers every rack.

At end of life, blocks are taken back for assessment and cell recovery through a licensed recycler, with the chain of custody documented.

Method statements

Written per site, issued before mobilisation, not adapted from a template.

DC safety

Isolation, lock-out and proven-dead procedures for 1,331 V DC systems.

Fire response

Site-specific emergency plan agreed with the local fire authority.

End of life

Take-back and licensed recycling with documented chain of custody.

Next step

Start with the data you already have.

A year of 15-minute load data, a PPA profile or a tender document is enough for a first sizing. We will tell you what is missing before we quote.